By Noelle H. Lowery
While not officially on the Marco Island City Council’s agenda for its Monday, Feb. 2 regular meeting, the $15 million Rose Marina redevelopment project took center stage. Council is slated to discuss the project at its regular Feb. 17 meeting.
At issue were continued citizen concerns about the temporary use permits being applied for by Rose Marina that would allow it to use three sites for boat storage, construction staging and temporary parking during the 6-12 month project. The problem: The site designated for the temporary boat storage is located on four residentially-zoned vacant lots now owned by Rose Marina, and homeowners in surrounding the lots are not happy.
In fact, seven of them addressed city councilors during the Community Forum portion of the meeting. The citizens came armed with copies of internal city emails between Rose Marina representatives and City Zoning Administrator Tami Scott, questioning whether temporary boat storage was an allowed use for a temporary use permit under the city’s Land Development Code and whether deed restrictions on the lots prohibit the use as well.
Then there were the owls — two burrowing owl nests that were discovered on the vacant lots in question. Over the past couple of weeks, some citizens noticed that the two owl nests had been destroyed and began reporting the act to city officials.
During the City Council meeting, it was reported that representatives from Rose Marina had lawfully obtained a permit from the Florida Fish and Wildlife Conservation Commission to remove the nests from the lots in preparation for the project. A copy of the Migratory Bird Nest Removal permit indicates that Rose Marina was authorized to destroy “inactive” (those containing no eggs or flightless young) burrowing owl nests “in association with seawall renovations.”
Council Chairman Larry Sacher assured the citizens that they — and the many others who had contacted City Hall about the Rose Marina project — were being heard and that their concerns would be considered when City Council addressed the project during the Feb. 17 meeting.
In other business, City Council also:
He added that he sent a notice of non-compliance to QE with a demand that the president of the company come before City Council to provide a schedule for how the contractor is going to bring the project back into compliance.
The set back is a big one for the city. Readers will remember that the ownership group for the Marco Island Marriott Beach Resort kicked in an extra $1 million to expedite the bridge project, taking the construction timeline from 18 to 10 months. The motive was to eliminate any potential overlap between the bridge work and construction of the Marriott’s $150 million renovation project.
City officials now must consider their options, including shutting down the project until it can be brought back into compliance or being prepared to assess daily liquidated damages against QE to the tune of $6,242 per day when the time comes. As it stands, Pinter and his staff are considering withholding the monthly $100,000 payment for the expedited schedule. To date, QE has received $400,000 as partial payment for this abbreviated sc